Job Shop Planning Board Workbench Gantt
The Gantt section of the Job Shop Planning Board (tisfc8372m000) allows you to view the scheduled job shop planning operations.
You can select Production Order tab to view the operations grouped by production orders in the Gantt. You can select the Schedule View tab to view the operations grouped by Work Centers and Machines (Machine Types) in the Gantt.
Machine Operations: The list of machine operations
for the selected production order/operation.
Note:
- The Machine Operations tab is displayed only if the Job Shop by Siteis set to Active in the Implemented Software Components (tccom0100s000) session.
- The machine operations are displayed only if machine operations are linked to the production order or operation.
- The formula to calculate the Duration and Remaining Production Qty:
Duration = Planned Setup Time + Planned Run Time
Remaining Production Qty = Planned Production Qty - Rejected Qty - Completed Qty
These context actions are available:
- Gantt: Create Production Order, Job Shop Schedule Runs.
- Production Order: Release, Reschedule, Report Order Complete, Pegging-Upstream, Pegging-Downstream, Transfer Planned Production Orders, Print Production Order Documents.
- Operation: Report Operation Complete, Drag and Drop of an operation to change operation time, Machine Availability to record Machine Breakdown time of an operation. The Fix dates for Planning and Scheduling to select the Fixed Planning Dates for an Operation, and the Locked for Scheduling for a Operation.
Note:
- If the Job Shop by Site field is set to Inactive, the menu title is .
- The lock symbol is displayed on the Operation, if a flag is selected.