Exporting/Importing PCS Activities via XML
- Click Project Control in Manufacturing to Microsoft Project or another project application. to transfer data from
- Click Project Control in Manufacturing. to transfer data from Microsoft Project or another project application to
After the XML file is imported in the external project application, you can plan or replan the project data. Note that the dates in Microsoft Project can deviate from the dates in LN. Especially if you ran the Generate Network Planning (tipcs4210m000) session in LN before the import, the dates will differ. The is reason is that Microsoft Project uses a planning logic that differs slightly from LN.