Displaying Shared Work Center Utilization by Day
Before you can use this session you must run the Build Utilization (tisfc0201m000) session (in the work center's company). You must select Automatic or Manual in the Update Method Day Utilization field and Automatic or Manual in the Update Method Week Utilization field in the Production Order Parameters (tisfc0100s000) session to update the plans on a daily basis.
In the Shared Work Center Relationships (tirou3100m000) session, you defined the Percentage Capacity of the primary work center allocated to the current secondary work center. That determines the capacity of the secondary work center. If the primary work center has a capacity of 80 hours per week and the current secondary work center has a Percentage Capacity of 50%, its capacity will be 40 hours.