Displaying Shared Work Center Utilization

You can define which secondary work centers share a primary work center's capacity in the Shared Work Center Relationships (tirou3100m000) session.

To regenerate utilization data, run the Build Utilization (tisfc0201m000) session for the primary work center's company and the secondary work center's company. You can change company from the Tools menu of your Desktop Manager or Menu Browser.

To see the shared work center's utilization, on the appropriate menu, click:

  • Shared Work Center Utilization by Week, to start the Shared Work Center Utilization by Week (tisfc1508m000) session.
  • Shared Work Center Utilization by Day, to start the Shared Work Center Utilization by Day (tisfc1509m000) session.

Reports

By selecting Print from the File menu, you can start the following sessions:

  • Print Shared Work Center Utilization by Week (tisfc1405m000).
  • Print Shared Work Center Utilization by Day (tisfc1406m000)