Rescheduling Production Orders
To reschedule a range of JSC production orders in the Replan Production Orders (tisfc3240m000) session by order or order group:
-
Select By Group in the selection range.
-
Select to which site the selection applies, if multisite functionality is activated.
-
Select a range of JSC Order Groups in the Group Selection group box.
- Select the desired print options in the Processing Print Options group box.
- Click Select Orders for Replanning (tisfc3140m000) session starts. This session displays a list of all JSC production orders falling within the selection range. . The
- Per production order, change the Modified Production Start Date and the Modified Requested Delivery Date.
- On the appropriate menu, click .
- If you selected one or more print options, the Select Device (ttstpsplopen) session starts. Specify an output device for printing the reports.
- Click . The selected orders are rescheduled and a report is printed.