Data mapping: import data from Microsoft Project to PCS

If you work on Microsoft Project, use the Export / Import PCS Activities via XML (tipcs4172m000) session to transfer project data from Microsoft Project to Project Control in LN. The table shows how data in Microsoft Project matches the data in . Project Control. Only a limited number of fields in Project Control is updated.

Microsoft Project task field (in XML) LN activity field code LN field name
EarlyStart tipcs400.esdt Earliest Start Date
LateStart tipcs400.lsdt Latest Start Date
EarlyFinish tipcs400.efdt Earliest End Date
LateFinish tipcs400.lfdt Latest End Date
Start tipcs400.dsdt Desired Start Date
Free Slack tipcs400.totf Free Float
Total Slack tipcs400.fref Total Float
Finish tipcs400.dfdt Desired End Date
The following fields are only updated if the Automatic Update check box in the Activity Overview by Project (tipcs4502m000) session is cleared:
PercentComplete tipcs400.pctc Percentage Completed
ActualStart tipcs400.asdt Actual Start Date
ActualFinish tipcs400.afdt Actual End Date
Note: 

The Free Float and Total Float fields are expressed in days, but the MS Project Slack fields are expressed in hours.

The conversion is based on the Work Center field and the Basic Day Capacity field linked to the specified work center.