To calculate production times of operations
To offset lead-times, and to calculate start dates, end dates, and delivery dates, LN must know, among others, the production time of operations. This topic describes the method LN applies to calculate the production time of an operation.
The method LN uses to calculate the production time first of all depends on whether or not the operation has a fixed duration. You can use the Fixed Duration check box in the Production Planning (tisfc0110m000) session to make the appropriate setting.
LN uses the data of these sessions to get operation lead times for production planning.
Production time of an operation
If you do not select the Fixed Duration check box in the Production Planning (tisfc0110m000) session, LN applies the following formula to calculate the production time of an operation:
production time = average setup time + cycle time
The order quantity (batch size) in this calculation is the quantity planned input.
Operation with fixed duration
If you select the Fixed Duration check box in the Production Planning (tisfc0110m000) session, LN applies the following formula to calculate the production time of an operation:
production time = average setup time + cycle time
You can define the default value for fixed duration in the following sessions:
-
Task Relationships (tirou0104m000), which defaults the fixed duration value to:
- Generic Routing (tipcf3120m000) (for operations in a generic routing).
- Routing Operations (tirou1102m000)