Subcontracting Bill of Material (tisub1110m000)
Use this session to manage subcontracting bill of material (BOM)
Field Information
- Product
-
The subcontracted item.
- Subcontractor
- Subcontractor Site
-
The ID of the site where subcontracted work is performed.
- Ship-from Business Partner
-
The business partner who ships the subcontracted part.
- Revision
-
The revision ID.
- Site
-
The site ID.
Note: Only visible if multisite functionality is active. - Position
-
The subcontracted item's position number.
- Material
-
The item that is a component of the received main item.
- Supplied by Subcontractor
-
If you subcontract one or more operations, or an item's entire production process, you can choose whether or not to send material to the subcontractor to use for the subcontracted item.
- If this check box is selected, the material is not sent to the subcontractor. The material is supplied by the subcontractor.
- If this check box is cleared, and the material is linked to a subcontracted operation, the material is sent to the subcontractor.
- Net Quantity in BOM Unit
-
The net quantity to be specified in BOM unit. To use a BOM unit that is other than the item unit, there must be an approved conversion factor. If the item unit is different than the BOM unit, the net quantity in item unit is calculated based on the approved conversion factor.
Note: This field is enabled only if:- The BOM Units of Material Lines check box is selected in the Product Engineering Parameters (timfc0100m000) session.
- The Use BOM Units check box is selected in the Product Subcontractors List (tisub1100m000) session.
- The Status of the Product Subcontracting Model is set to New.
- Net Quantity
-
The number of items on the BOM line to which the reference designator applies. A reference designator can apply to one or more items on the BOM line.
- BOM Unit
-
The unit in which the related Net and Scrap quantities are expressed.
Note: This field is enabled only if:- This field is enabled only if:
- The BOM Units of Material Lines check box is selected in the Product Engineering Parameters (timfc0100m000) session.
- The Status of the Production Bill of Material is set to New.
- If the Use Bom Units check box is selected, the value specified for the BOM Unit is defaulted to the value of the item unit.
- This field is enabled only if:
- Scrap (%)
-
The percentage of material that is lost during production.
- Warehouse
-
The warehouse from which materials are shipped to the subcontractor.
- Supply System
-
The supply system used.
- Lot Selection
-
The lot code of the product.
- Inherit Demand Peg
-
If this check box is selected, the dependent components will inherit the project peg of the main item.
- Floor Stock
- Indicates if the item is a floor stock item.
- Visible on Order
- If this check box is selected, the material is
visible on order.Note:
- This check box is cleared if the check box is selected. In other cases, this check box is selected. It can only be enabled for floor stock items.
- This check box is displayed only if the Implemented Software Components (tccom0500m000) session. check box is selected in the