Order Block Sequencer (tisfc4220m000)

Use this session to group and sequence machine operations for a machine capacity group that contains a changeover critical machine for a plan group and site combination.

Field Information

Site

The site for which the machine operations are sequenced.

Plan Group

The plan group to which machine operations are sequenced.

Work Center

The work center within the plan group for which the machine operations are sequenced.

Machine Type

The machine type within the plan group for which the machine operations are sequenced.

Machine Number

The machine number within the plan group for which the machine operations are sequenced.

Start Date

The date the first sequenced machine operation is scheduled to start.

Horizon Date

The last date for which machine operations are obtained for sequencing. The original planned finish date of the machine operation is used as a selection criterium.

Exclude Orders of previous Block Runs

If this check box is selected, machine operations that have been sequenced in previous runs are excluded from sequencing.

Delete previous Block Runs

If this check box is selected, the previously sequenced block runs are deleted.

Automatic Update Production Orders

If this check box is selected, the production orders the machine operations belong to are automatically updated after sequencing.