Aggregate Machine Operation Quantities (tisfc4201m000)

Use this session to roll up machine operation quantities to the production order operation.

The roll up is from first to last machine operation per order.

Note: 
  • The production order must have the status Released.

    Operations with the Report Product parameter in the Production Planning (tisfc0110m000) session set to By Machineare aggregated.

  • If the Aggregate Machine Operation Quantities parameter in the Production Order Settings History by Site (tisfc0181m000) session is set to Manual, you must use this session for aggregation. If the parameter is set to Report Shift, using this session to aggregate is optional.

Field Information

Site

The site ID.

Order Selection Range

If this check box is selected, you can select a range of production orders for aggregation.

Production Order

The production order range.

Production Start Date and Time

The start date and time range of the production order selection.

Planned Delivery Date

The planned delivery date of the production order selection.

From Item

The item range of the production orders.

Machine Capacity Group Selection

If this check box is selected, you can select a range of machine capacity groups for aggregation.

Work Center

The work center for which the selection is made.

Machine Type

The machine type used for manufacture.

Shift

The range of shifts to which aggregation applies.

End

The shift range end date and time.

Start

The shift range start date.

Process Report

If this check box is selected, a process report is generated during aggregation.

Error Report

If this check box is selected, an error report is generated during aggregation.