Report Shift (tisfc4112m000)
You can view additional data in these sessions:
- Machine Operation Quantities (tisfc4101m000)
- Correct Machine Operation Quantities (tisfc4101m200)
- Machine Hours (tisfc4102m000)
- Machine Time Stamps (tisfc4111m000)
Field Information
-
- Site
-
The site ID.
- Production Department
-
Select the range of production departments for which you want to view machine operations.
- Supervisor
-
Select the range of employees for who you want to view the machine operations. Each employee is responsible for one or more work centers.
- Work Center
-
Select the range of work centers for which you want to see machine operations.
-
- Released
-
If this check box is selected, machine orders with the status Released and their number are displayed.
- Active
-
If this check box is selected, machine operations with the status Running and their number are displayed.
- Completed
-
If this check box is selected, machine operations with the status Finished and their number are displayed.
-
- Past
-
If this check box is selected, shifts closed before the current date are displayed.
- Current
-
If this check box is selected, shifts currently active are displayed.
- Future
-
If this check box is selected, shifts with the start date in the future are displayed.
-
- Machine Number
-
The machine designation.
- Production Order
- Operation
-
The operation ID.
- Machine Sequence
-
The sequence number of the machine operation.
- Item
-
The end item produced.
- Planned
-
The total quantity of product required.
- Planned
-
The quantity of product planned for production.
- Completed
-
The quantity of product completed.
- Rejected
-
The quantity of product rejected during the shift.
- Unit
- Planned Finish
-
The date and time the employee finishes work on the project activity.
- Shift
-
The shift ID.
- Shift (GUID)
-
The unique ID for the shift.
- Shift Start Date
-
The date and time the selected shift started.
- Shift End Date
-
The date and time the selected shift ended.
- Shift Aggregated
-
If this check box is selected, the selected shift capacity was aggregated to work center.
- Machine Hours Posted
-
If this check box is selected, machine hours have been posted.
- Shift Completed
-
The date and time the selected shift was reported completed.
- Quantity Reporting is Completed
-
If this check box is selected, all quantities have been reported for the selected shift.
- Aggregated to Operation
-
If this check box is selected, machine hours have been aggregated to operation.
- Machine Operation Status
-
The status of the machine is:
Allowed values
- Released
- Setup
- Running
- Interrupted
- Finished
- Closed
- Initial
- Site
-
The ID of the site.
- Production Department
- Supervisor
-
The name of the employee responsible for overseeing the shift.
- Work Center
-
The work center ID.
- Machine Type
- Shift in Planning
-
If this check box is selected, the machine operation has been replanned. If the check box is cleared the machine operation can be shifted in planning if the machine operation has not yet started.