Machine Operations (tisfc4100m000)
Field Information
- Site
-
The site where production will take place.
- Production Order
-
The planned production order ID.
- Order Status
-
The order status of the production order.
Allowed values
- Created
-
The initial status of a production order. All production order data can still be changed. Materials are not issued yet. Materials can be added or removed, and quantities can be changed.
- Modify
-
The production order may be modified in the same way as with the Created status. If the Version Control check box is selected, this status is assigned to a newly created version of a production order. It is possible to adjust estimates for this production order. The already registered actuals are saved with the new version number on the production order.
Note: You must print the production order documents and release the production order once you have made the necessary changes. Once the new production order is printed, or released the estimated costs are frozen again. - Scheduled
-
The production order receives this status after being scheduled in Infor SCM Scheduler . This status is only applicable if Infor SCM Scheduler is Active.
- Printed
-
The documents for the production order were printed. If the Printing Production Order Documents Mandatory check box is selected in the Production Order Parameters (tisfc0100s000) session, the production order cannot be released before the order documents are printed. The Printing Production Order Documents Mandatory check box is not valid for repetitive items, because printing order documents is never mandatory for repetitive items. For a description of the types of order documents, see Contents of order documents.
Note: Once the production order documents are printed, estimates for the order can no longer be adjusted. - Released
-
If a production order is released for production, materials are issued to the job shop for production, and hours can be posted. You can still perform the following:
- Adjust planning data
- Change the estimated materials and estimated operation costs as long as the cost estimates are not frozen.
Production orders can be released in the Release Production Orders (tisfc0204m000) session.
- Active
-
Work on the production order has started. The order status becomes Active when any WIP transaction takes place for the production order. If the production order status is Active, hours are posted and materials are issued. The estimated costs cannot be changed .
- Production Completed
-
The order is reported as completed. When Warehousing finishes the inbound procedure for produced items that must be delivered into inventory, the production receives the Completed status.
- Completed
-
The order is reported as completed and all completed products were delivered into inventory. You can still account hours and issue materials for the production order. You can report an order as completed in these sessions:
-
Report Orders Completed (tisfc0520m000)
Use this session to report one or more orders, partly or entirely, as completed. -
Report Operations Completed (tisfc0130m000)
Use this session to report the final operation of an order as completed. -
Report Operations Complete by Order Group (tisfc0205m000)
Use this session to report orders as completed by order group. -
Report Production Schedules Completed (tirpt1201m000) and Report Production Orders Completed from Production Schedule (tirpt1502m000)
Use these sessions to report production orders in production schedules as complete for RPT items.
-
- Closed
-
The financial results of the production order have been calculated. Before a production order is closed, all materials for the order must have been issued and all hours must have been accounted. Purchase orders for subcontracted operations must have been processed. After an order has been closed, materials can no longer be issued nor can hours be accounted unless the order status is reset. You can close production orders with the Close Production Orders (ticst0201m000) session.
- Archived
-
The production order data was moved to the archive. For more information, refer to Archiving production orders.
- Operation
-
The planned operation for which a machine operation must be generated.
- Operation Status
-
The current operation status.
Allowed values
- Planned
-
The status when the plan is created.
- Ready to Start
-
When there is enough Quantity Completed on all the previous operations to report complete the minimum order quantity of the operation in the Report Operations Completed (tisfc0130m000) session, the operation status is set to Ready to Start by the previous operation.
- Started
-
If you use LN the operation status is Started when any quantity is reported as completed in Job Shop Control .
- Active
-
A WIP transaction has been performed on this operation. When the first operation is set to Active, the order status becomes Active too.
- Blocked
-
The operation has been blocked in Job Shop Control by the user or by an inspection order. Refer to Blocking operations.
- Completed
-
All the work has been completed for the operation. The quantities reported as completed and rejected are final. You can set this status in the Report Operations Completed (tisfc0130m000) details session. If required, you can click in the Report Operations Completed (tisfc0130m000) details session to change the operation status from Completed back to Active.
- Closed
-
The financial results of the operation have been calculated. Operations can only be closed in LN.
- Machine Sequence Number
-
The sequence number of the machine operation.
- Work Location
-
- Work Center
-
The work center where production will take place.
- Machine Type
-
The machine type needed for production.
- Machine Number
-
The designation of the machine.
- Planning Related
-
- Item
-
The product ID.
- Quantity Planned Input
-
The planned input for the operation.
- Setup
-
- Planned Set Up Scrap
-
The quantity of lost product expected during the operation.
Note: If the scrap quantity is increased, LN increases the quantity planned input to compensate and keep the quantity of planned output the same. - Planned Setup Time
-
The expected setup time for the specified operation.
- Planned Setup Start Date
-
The date LN plans to start the setup for the operation.
- Planned Setup Finish Date
-
The date LN plans to finish setup for the operation.
- Actual Setup Start Date
-
The date the setup for the operation was started.
- Actual Setup Finish Date
-
The date the setup for the operation was completed.
- Production
-
- Yield Percentage
-
The expected yield in percentages for the selected operation.
- Planned Production Quantity
-
The quantity planned to be produced.
- Planned Process Time
-
The time LN expects to be needed to produce the planned quantity.
- Planned Run Time
-
The time LN expects is needed for the machines to be running to produce each piece of the operation.
- Planned Production Start Date
-
The date LN expects processing to start.
- Planned Production Finish Date
-
The date LN expects processing to finish.
- Actual Production Start Date
-
The date processing started.
- Actual Production Finish Date
-
The date processing finished.
- Miscellaneous
-
- Locked for Scheduling
-
If this check box is selected, the selected operation cannot be moved by the Job Shop Scheduler.
- Report Product
-
Product completion is reported by:
Allowed values
-
Manual
Reporting is done manually in the Machine Work List (tisfc4600m000) session. -
By Machine Group
Reporting is done by machine in the Report Operations Completed (tisfc0130m000) session.
-
- Report Machine Hours
-
Material use is reported by:
Allowed values
-
Backflush
This is an automatic calculation based on reported quantities. -
Manual
Reporting is done by an employee. -
By Machine Group
Reporting is done by machine in the Report Operations Completed (tisfc0130m000) session.
-
- Machine Operation Status
-
The status of the machine is:
Allowed values
- Released
- Setup
- Running
- Interrupted
- Finished
- Closed
- Initial
- Reporting
-
- Quantity Reporting is Completed
-
The percentage of the planned process quantity completed.
- Quantity Completed
-
The total quantity completed for the production order.
- Quantity Rejected
-
The total quantity rejected for the production order.