Work Center Input/Output Control (tisfc3510m000)

Use this session to see a summary of the planned and actual input and output values for a work center.

You can start the following sessions from the appropriate menu:

  • Generate Work Center Input/Output Control (tisfc3210m000)
  • Delete Work Center Input/Output Control (tisfc3212m000)
Note: If you want to see input/output data for a machine, use the Machine Input/Output Control (tisfc3520m000) session.

Field Information

Site

The site ID.

Note: Only visible if multisite functionality is active.

Work Center

The work center for which you want to compare actual and planned inputs and outputs. Note that you can only see data for work centers whose Critical in Master Planning check box is selected in the Work Centers (tirou0101m000) session.

Description

The work center for which you want to compare actual and planned inputs and outputs. Note that you can only see data for work centers whose Critical in Master Planning check box is selected in the Work Centers (tirou0101m000) session.

Desired Queue

The desired queue that is defined for the work center in the Work Centers (tirou0101m000) details session.

Planned Input

planned input

Actual Input

actual input

Input Cumulative Deviation

The sum of the differences between the planned input and the actual input for the current target period and all the target periods before the current one for which you have data.

Planned Output

planned output

Actual Output

actual output

The value of the actual output depends, among other things, on the setting of the Include Partial Completions (Default) check box in the Generate Work Center Input/Output Control (tisfc3210m000) session.

Output Cumulative Deviation

The sum of the differences between the planned output and the actual output for the current target period and all the target periods before the current one, for which you have data.

Planned Queue

planned queue

Actual Queue

actual queue

Queue Deviation

queue deviation

Desired Queue Deviation

The actual queue minus the desired queue.

Available Capacity

available capacity

Demonstrated Load Factor

demonstrated load factor

Ending Date

The last day of the target period.

Available Labor Resources (FTE)

The number of operators that is available on the work center.

Labor Hours

The number of man hours that are desired on the work center, given the desired queue.

Man hours = Number of operators on the work center * Desired queue

Number of Machines

The number of machines that is available on the work center.

Machine Hours

The number of machine hours that are desired on the work center, given the desired queue.

Machine hours = Number of machines on the work center * Desired queue

Planned Input

planned input

Actual Input

actual input

Input Cumulative Deviation

The sum of the differences between the planned input and the actual input for the current target period and all the target periods before the current one for which you have data.

Planned Output

planned output

Actual Output

actual output

Output Cumulative Deviation

The sum of the differences between the planned output and the actual output for the current target period and all the target periods before the current one, for which you have data.

Planned Queue

planned queue

Actual Queue

actual queue

Queue Deviation

queue deviation

Desired Queue Deviation

The actual queue minus the desired queue.

Available Capacity

available capacity

Demonstrated Load Factor

demonstrated load factor