Shared Work Center Utilization by Day (tisfc1509m000)

Use this session to display an overview of capacity utilization for a shared work center for one day. You can see, for each order, the time and quantity that it is planned to occupy the work center. You can only use this session if you have selected Automatic or Manual in the Update Method Day Utilization field of the Production Order Parameters (tisfc0100s000).

Field Information

Site

The site ID.

Note: Only visible if multisite functionality is active.

Work Center

The shared work center whose planned capacity utilization you want to see.

Company

The company of the shared work center.

Production Date

The day for which the planned capacity utilization for the work center is displayed.

Work Center

The secondary work center whose planned capacity utilization you want to see.

Normal Man Capacity

The secondary work center's normal capacity expressed in man hours.

The normal capacity is calculated from the following fields in the Work Centers (tirou0101m000) session:

Number of Operators	* Basic Day Capacity by Resource Unit.
Available Man Capacity

The secondary work center's available capacity expressed in man hours.

The available capacity is calculated as follows:

Capacity in	calendar * Number of Operators * Percentage Shared Capacity. 

Where:

Capacity in	calendar = Calendar Time * Efficiency Factor * Percentage Capacity.
				
  • Calendar time = end date - start date (for one record in the actual calendar).
  • Efficiency Factor = working time / clock time.
  • Percentage Shared Capacity = the percentage allocated to the shared secondary work center. In case of a primary shared work center or no shared work center, the percentage is 100%.

Total Labor Hours

An aggregation of the secondary work center's remaining/outstanding operation hours for the specified period expressed in man hours.

Because these are remaining hours, the spent hours booked in People , are not counted.

Normal Machine Capacity

The secondary work center's normal capacity expressed in machine hours.

The normal capacity is calculated from the following fields in the Work Centers (tirou0101m000) session:

Number of Machines	* Basic Day Capacity by Resource Unit. 
Available Machine Capacity

The secondary work center's available capacity expressed in machine hours.

The available capacity is calculated as follows:

Capacity in	calendar * Number of Machines * Percentage Shared Capacity. 

Where:

Capacity in	calendar = Calendar Time * Efficiency Factor * Percentage Capacity.
				
  • Calendar time = end date - start date (for one record in the actual calendar).
  • Efficiency Factor = working time / clock time.
  • Percentage Shared Capacity = the percentage allocated to the shared secondary work center. In case of a primary shared work center or no shared work center, the percentage is 100%.

Total Mach. Hours

An aggregation of the secondary work center's remaining/outstanding operation hours for the specified period expressed in machine hours.

Because these are remaining hours, the spent hours booked in People , are not counted.

Work Center

primary work center

Company

The company of the primary work center.

Normal Man Capacity

The primary work center's normal capacity expressed in man hours.

The normal capacity is calculated from the following fields in the Work Centers (tirou0101m000) session:

Number of Operators	* Basic Day Capacity by Resource Unit. 
Available Man Capacity

The primary work center's available capacity expressed in man hours.

The available capacity is calculated as follows:

Capacity in	calendar * Number of Operators * Percentage Shared Capacity. 

Where:

Capacity in	calendar = Calendar Time * Efficiency Factor * Percentage Capacity.
				
  • Calendar time = end date - start date (for one record in the actual calendar).
  • Efficiency Factor = working time / clock time.
  • Percentage Shared Capacity = the percentage allocated to the shared secondary work center (in case of a primary shared work center or a no shared work center, the percentage is 100%.

Total Labor Hours

An aggregation of the primary work center's remaining/outstanding operation hours for the specified period expressed in man hours.

Because these are remaining hours, the spent hours booked in People , are not counted.

Normal Machine Capacity

The primary work center's normal capacity expressed in machine hours.

The normal capacity is calculated from the following fields in the Work Centers (tirou0101m000) session:

Number of Machines	* Basic Day Capacity by Resource Unit. 
Available Machine Capacity

The primary work center's available capacity expressed in machine hours.

The available capacity is calculated as follows:

Capacity in	calendar * Number of Machines * Percentage Shared Capacity. 

Where:

Capacity in	calendar = Calendar Time * Efficiency Factor * Percentage Capacity.
				
  • Calendar time = end date - start date (for one record in the actual calendar).
  • Efficiency Factor = working time / clock time.
  • Percentage Shared Capacity = the percentage allocated to the shared secondary work center. In case of a primary shared work center or a no shared work center, the percentage is 100%.

Total Mach. Hours

An aggregation of the primary work center's remaining/outstanding operation hours for the specified period expressed in machine hours.

Because these are remaining hours, the spent hours booked in People , are not counted.

Start Time

The production date to which the utilization applies.

Machine

The machine on which the operation is carried out.

Production Order

The planned production order.

Routing

The routing of the planned production order at the shared work center.

Operation

The operation carried out at the shared work center.

Task

The task carried out at the shared work center.

Quantity Planned

The quantity you plan to produce in the current operation at the shared work center.

Labor Hours

The man hours needed to carry out the operation.

Machine Hours

The machine hours needed to carry out the operation.

Physical Location

The location where the operation is carried out on the shop floor. You can also use this field to enter other information about the production order.

Production Order Group

The production order group to which the production order belongs.

Item

The end-item produced by the production order.