Shared Work Center Utilization by Week (tisfc1508m000)
Use this session to view the capacity planned for a shared work center in a specified week.
In the Shared Work Center Relationships (tirou3100m000) session, you defined the Percentage Capacity of the primary work center allocated to the current secondary work center. That determines the capacity of the secondary work center. If the primary work center has a capacity of 80 hours per week and the current secondary work center has a Percentage Capacity of 50%, its capacity will be 40 hours.
Field Information
- Site
-
The site ID.
Note: Only visible if multisite functionality is active. - Work Center
-
The shared work center whose planned capacity you want to see.
- Company
-
The company of the shared work center.
- Production Year
-
The year for which you want to view the planned shared work center utilization.
- Production Week
-
The week number for which you want to view the planned shared work center utilization.
Week one is the first week of the year containing at least four days, assuming that Monday is the first day of the week.
- Work Center
-
The secondary work center whose planned capacity you want to see.
- Normal Man Capacity
-
The secondary work center's normal capacity expressed in man hours.
The normal capacity is calculated from the following fields in the Work Centers (tirou0101m000) session:
Number of Operators * Basic Day Capacity by Resource Unit.
- Available Man Capacity
-
The secondary work center's available capacity expressed in man hours.
The available capacity is calculated as follows:
Capacity in calendar * Number of Operators * Percentage Shared Capacity.
Where:
Capacity in calendar = Calendar Time * Efficiency Factor * Percentage Capacity.
- Calendar time = end date - start date (for one record in the actual calendar).
- Efficiency Factor = working time / clock time.
- Percentage Shared Capacity = the percentage allocated to the shared secondary work center. In case of a primary shared work center or no shared work center, the percentage is 100%.
- Total Labor Hours
-
An aggregation of the secondary work center's remaining/outstanding operation hours for the specified period expressed in man hours.
Because these are remaining hours, the spent hours booked in People , are not counted.
- Normal Machine Capacity
-
The secondary work center's normal capacity expressed in machine hours.
The normal capacity is calculated from the following fields in the Work Centers (tirou0101m000) session:
Number of Machines * Basic Day Capacity by Resource Unit.
- Available Machine Capacity
-
The secondary work center's available capacity expressed in machine hours.
The available capacity is calculated as follows:
Capacity in calendar * Number of Machines * Percentage Shared Capacity.
Where:
Capacity in calendar = Calendar Time * Efficiency Factor * Percentage Capacity.
- Calendar time = end date - start date (for one record in the actual calendar).
- Efficiency Factor = working time / clock time.
- Percentage Shared Capacity = the percentage allocated to the shared secondary work center. In case of a primary shared work center or no shared work center, the percentage is 100%.
- Total Mach. Hours
-
An aggregation of the secondary work center's remaining/outstanding operation hours for the specified period expressed in machine hours.
Because these are remaining hours, the spent hours booked in People , are not counted.
- Work Center
-
The primary work center whose planned capacity you want to see.
- Company
-
The company of the primary work center.
- Normal Man Capacity
-
The primary work center's normal capacity expressed in man hours.
The normal capacity is calculated from the following fields in the Work Centers (tirou0101m000) session:
Number of Operators * Basic Day Capacity by Resource Unit.
- Available Man Capacity
-
The primary work center's available capacity expressed in man hours.
The available capacity is calculated as follows:
Capacity in calendar * Number of Operators * Percentage Shared Capacity.
Where:
Capacity in calendar = Calendar Time * Efficiency Factor * Percentage Capacity.
- Calendar time = end date - start date (for one record in the actual calendar).
- Efficiency Factor = working time / clock time.
- Percentage Shared Capacity = the percentage allocated to the shared secondary work center (in case of a primary shared work center or a no shared work center, the percentage is 100%.
- Total Labor Hours
-
An aggregation of the primary work center's remaining/outstanding operation hours for the specified period expressed in man hours.
Because these are remaining hours, the spent hours booked in People , are not counted.
- Normal Machine Capacity
-
The primary work center's normal capacity expressed in machine hours.
The normal capacity is calculated from the following fields in the Work Centers (tirou0101m000) session:
Number of Machines * Basic Day Capacity by Resource Unit.
- Available Machine Capacity
-
The primary work center's available capacity expressed in machine hours.
The available capacity is calculated as follows:
Capacity in calendar * Number of Machines * Percentage Shared Capacity.
Where:
Capacity in calendar = Calendar Time * Efficiency Factor * Percentage Capacity.
- Calendar time = end date - start date (for one record in the actual calendar).
- Efficiency Factor = working time / clock time.
- Percentage Shared Capacity = the percentage allocated to the shared secondary work center. In case of a primary shared work center or a no shared work center, the percentage is 100%.
- Total Mach. Hours
-
An aggregation of the primary work center's remaining/outstanding operation hours for the specified period expressed in machine hours.
Because these are remaining hours, the spent hours booked in People , are not counted.
- Day
-
The production date to which the utilization applies.
- Machine
-
The machine for which you want to see the planning in the company of the shared work center.
- Production Order
-
The planned production order.
- Routing
-
The routing of the planned production order at the shared work center.
- Operation
-
The code of the operation carried out at the shared work center.
- Task
-
The task planned at the shared work center.
- Quantity Planned
-
The quantity planned to be produced by the production order at the shared work center.
- Labor Hours
-
The man hours needed to carry out the operation.
- Machine Hours
-
The machine hours needed to carry out the operation.
- Physical Location
-
The location where the operation is carried out. You can also enter other information about the operation in this field.
- Production Order Group
-
The production order group to which the production order belongs.
- Item
-
The item planned to be produced by the production order.