Machine Utilization by Day (tisfc1505m000)
Use this session to display an overview of capacity utilization of a machine for one day. You can see, the time and quantity that it is planned for the machine.
You can only use this session if you have selected Automatic or Manual in the Update Method Day Utilization field of the Production Order Parameters (tisfc0100s000) session.
Field Information
- Site
-
The site ID.
Note: Only visible if multisite functionality is active. - Machine
-
The machine for which you want to see how much you have planned for it for a day.
- Description
-
The machine for which you want to see how much you have planned for it for a day.
- Normal Capacity
-
The normal capacity of the machine for one day. You can modify this in the Basic Day Capacity field in the Machines (Machine Types) (tirou0102m000) session.
- Production Date
-
The day for which you want to see how many hours you have planned to use the machine for.
- Total Machine Hours
-
The amount you have planned to use the machine on the day in question.
- Setup+Run Start Date
-
The start of the period for which you want to see how much you have planned the machine.
- Production Order
-
The code of the production order.
- Item
-
The item planned to be made by the machine.
- Routing
-
Note: If no routing is displayed, there are no estimated production costs defined for the production order.
- Operation
-
The code of the operation planned for the machine.
- Work Center
-
The work center where the machine carries out the operation.
- Machine Hours
-
The machine hours needed to carry out the operation
- Quantity Planned
-
The quantity of items you plan to produce with the machine during this time period, including items lost to scrap and low yield.
- Physical Location
-
The location where you plan to process the order.
- Production Order Group
-