Utilization by Day (tisfc1503m000)
Use this session to display an overview of capacity utilization for one day. You can see, for each order, the time and quantity that it is planned to occupy a work center and machine.
You can only use this session if you have selected Automatic in the Update Method Day Utilization field of the Production Order Parameters (tisfc0100s000) session.
Field Information
- Site
-
The site ID.
Note: Only visible if multisite functionality is active. - Date
-
The date for which you want to see how the quantity of time and materials you have planned.
- Machine Hours
-
The machine hours needed to carry out the operation
- Start Time
-
The start of the period for which you want to see what capacity has been planned.
- Work Center
-
The code of the work center where the operation is carried out.
To see utilization for a shared work center, use the Shared Work Center Utilization (tisfc1510m000) session.
- Description
-
The description of the work center where the operation is carried out.
To see utilization for a shared work center, use the Shared Work Center Utilization (tisfc1510m000) session.
- Machine
-
The machine with which the operation is carried out.
- Production Order
-
The code of the production order.
- Routing
-
Note: If no routing is displayed, there are no estimated production costs defined for the production order.
- Operation
-
The sequence number of the operation.
Operations do not have to follow in order of the sequence number. You can define the order in the Production Planning (tisfc0110m000) session.
- Quantity Planned
-
The quantity of items you plan to produce in this operation on this date, including items lost to scrap and low yield.
- Labor Hours
-
The man hours needed to carry out the operation