Utilization by Week (tisfc1502m000)
Use this session to display an overview of capacity utilization for one week. You can see, for each order, the time and quantity that it is planned to occupy a work center and machine.
Field Information
- Site
-
The site ID.
Note: Only visible if multisite functionality is active. - Production Year
-
The year for which you want to see the time and quantity planned.
- Production Week
-
The week for which you want to see an overview of the time and quantity planned. The week number is week of the year, where week one is the first week of the year containing at least four days, assuming that Monday is the first day of the week.
- Labor Hours
-
The man hours needed to carry out the operation
- Day
-
The date for which you want to see what capacity has been planned.
- Production Order
-
The order number for the planned operation.
- Operation
-
The sequence number of the operation.
Operations do not have to follow in order of the sequence number. You can define the order in the Production Planning (tisfc0110m000) session.
- Work Center
-
The work center where the work is planned to take place.
To see utilization for a shared work center, use the Shared Work Center Utilization (tisfc1510m000) session.
- Quantity Planned
-
The quantity of items you plan to produce in this operation on this date, including items lost to scrap and low yield.
- Machine
-
The machine with which the operation is carried out.
- Machine Hours
-
The machine hours needed to carry out the operation