Work Center Utilization by Week (tisfc1501m000)
Use this session to display an overview of capacity utilization for one work center for a week. You can see what orders have been planned, and how much time and materials they are expected to use.
Field Information
- Site
-
The site ID.
Note: Only visible if multisite functionality is active. - Work Center
-
The work center for which you want to see a summary of the capacity requirements planned for that week.
To see utilization for a shared work center, use the Shared Work Center Utilization (tisfc1510m000) session.
- Total Hours
-
The total number of man hours for all production orders that are planned to be carried out on the work center.
- Production Year
-
The year for which you want to display data about the planned work center utilization.
- Normal Capacity
-
The normal capacity of the persons on the work center is calculated as follows:
Normal Capacity = Number of Operators * Basic Week Capacity by Resource Unit.
The Available Labor Resources and the Week Capacity [Hours] are entered in the Work Centers (tirou0101m000) details session.
- Production Week
-
The week for which you want to see how much capacity has been planned for the work center.
- Available Capacity
-
The available capacity in hours per day for each employee or machine. Based on this capacity, the default duration of an activity is calculated using the appropriate formula.
- Day
-
The date for which you want to see what demands are planned for the work center.
- Production Order
-
The production order number.
- Item
-
The item that is produced in the operation.
- Machine
-
The machine with which the operation is carried out.
- Quantity Planned
-
The quantity of items you plan to produce in this operation at the work center on this date, including items lost to scrap and low yield.
- Operation
-
The code of the operation carried out at the work center.
- Physical Location
-
The location where the order is processed.
- Production Order Group
-
The group of orders to which the order belongs.
- Total Hours
-
The total number of machine hours for all production orders that are planned to be carried out on the work center.
- Normal Capacity
-
The normal capacity of the machines on the work center is calculated as follows:
Normal Capacity = Number of Machines * Basic Week Capacity by Resource Unit.
The Number of Machines and the Week Capacity [Hours] are entered in the Work Centers (tirou0101m000) details session.
- Available Capacity
-
The total capacity in machine hours that are planned to be available on the work center.
The available capacity is calculated as follows:
Number of machines * available number of hours according to the work center calendar (taking into account the capacity percentage defined for the calendar)