Work Center Utilization by Week (tisfc1501m000)

Use this session to display an overview of capacity utilization for one work center for a week. You can see what orders have been planned, and how much time and materials they are expected to use.

Field Information

Site

The site ID.

Note: Only visible if multisite functionality is active.

Work Center

The work center for which you want to see a summary of the capacity requirements planned for that week.

To see utilization for a shared work center, use the Shared Work Center Utilization (tisfc1510m000) session.

Total Hours

The total number of man hours for all production orders that are planned to be carried out on the work center.

Production Year

The year for which you want to display data about the planned work center utilization.

Normal Capacity

normal capacity

The normal capacity of the persons on the work center is calculated as follows:

Normal Capacity = Number of Operators * Basic Week Capacity by Resource Unit.

The Available Labor Resources and the Week Capacity [Hours] are entered in the Work Centers (tirou0101m000) details session.

Production Week

The week for which you want to see how much capacity has been planned for the work center.

Available Capacity

The available capacity in hours per day for each employee or machine. Based on this capacity, the default duration of an activity is calculated using the appropriate formula.

Day

The date for which you want to see what demands are planned for the work center.

Production Order

The production order number.

Item

The item that is produced in the operation.

Machine

The machine with which the operation is carried out.

Quantity Planned

The quantity of items you plan to produce in this operation at the work center on this date, including items lost to scrap and low yield.

Operation

The code of the operation carried out at the work center.

Physical Location

The location where the order is processed.

Production Order Group

The group of orders to which the order belongs.

Total Hours

The total number of machine hours for all production orders that are planned to be carried out on the work center.

Normal Capacity

normal capacity

The normal capacity of the machines on the work center is calculated as follows:

Normal Capacity = Number of Machines * Basic Week Capacity by Resource Unit.

The Number of Machines and the Week Capacity [Hours] are entered in the Work Centers (tirou0101m000) details session.

Available Capacity

The total capacity in machine hours that are planned to be available on the work center.

The available capacity is calculated as follows:

Number of machines * available number of hours according to the work center calendar (taking into account the capacity percentage defined for the calendar)