Print Shared Work Center Utilization by Week (tisfc1405m000)
Use this session to print a report showing what capacity usage is planned for a range of shared work centers. The capacity is shown for each primary work center, whose capacity is allocated to various secondary work centers.
Before you can use this session you must run the Build Utilization (tisfc0201m000) session. You must select Automatic or Manual in the Update Method Week Utilization field in the Production Order Parameters (tisfc0100s000) session
Field Information
- Min Man Utilization
-
Define a minimun percentage for the man utilization that LN must use as a criterion to select the work centers for which it must print a report.
The value that you define, acts like a filter.
- Min M/C Utilization
-
Define a minimun percentage for the man/capacity utilization that LN must use as a criterion to select the work centers for which it must print a report.
The value that you define, acts like a filter.
- Previous Operation Must be Completed
-
If this check box is selected, the only operations printed are:
- Start operations,
- Operations for which all previous operations have been completed.
The resulting report lists planned operations which can actually be started. No Help topic is associated with this item.
- Sort
-
Select which report is printed.
Allowed values
- by Week
- by Company by Week