Print Work Center Utilization by Week (tisfc1402m000)
Use this session to produce a report that shows how much you have planned to use a selection of work centers by week.
-
You can only use this session if you have selected Automatic or Manual in the Update Method Week Utilization field in the Production Order Parameters (tisfc0100s000) session.
- You can display an overview of work center usage in the Work Center Utilization by Week (tisfc1501m000) session.
- You can print shared work center utilization in the Print Shared Work Center Utilization by Week (tisfc1405m000) session.
- You can print a report that shows which operations you can start.
Field Information
- Previous Operation Must be Completed
-
If this check box is selected, the only operations printed are:
- Start operations,
- Operations for which all previous operations have been completed. No Help topic is associated with this item.
- Print Physical Location Data
-
If this check box is selected, any text you have entered about the location where the order is processed is also printed on the report.