Shift Production Planning (tisfc1202m000)
Use this session to shift the production planning. If you create a delay by postponing the production planning, you can use the delay, for example, to cope with a backlog in production.
Field Information
- Selection
-
Select how the production orders are chosen.
Allowed values
- By Order
- By Group
- Site
-
- Order
-
Enter the range of production orders whose operations you want to delay.
- Planner
-
The logon code of the employee who plans plan items.
- Shop Floor Planner
- Routing Group
- Product Line
- Product Class
- Selection Code
- Production Order Group
-
Enter the JSC order group whose production orders you want to shift.
- Current Date
-
The system date.
- Direction
-
The planning method that determines in which direction the production planning dates are shifted.
Allowed values
- Forward
- Backward
- Shift Planning to Date
-
The date to which you want to shift your production planning.
How the production planning is exactly shifted depends on whether you already worked on the production order:
- If no operations have Completed status, the date in the Shift Planning to Date field is considered as the start date of the production order's first operation. Depending on the value of the Direction field, backward planning or forward planning of the production order takes place, as from the Shift Planning to Date.
- If one or more operations have Completed status, the date in the Shift Planning to Date is considered the Start Date of the first operation with Active status. Depending on the value of the Direction field, backward planning or forward planning of the production order takes place, as from the Shift Planning to Date.
- If you select Backward in the Direction field, only production orders are shifted for which the first operation starts after the Shift Planning to Date.
- If you select Forward in the Direction field, only production orders are shifted for which the first operation starts before the Shift Planning to Date.
- Simulation
-
If this check box is selected, a report is generated listing the production orders that can be replanned, and the reasons if orders cannot be shifted.
- Message When Order is Late
-
If this check box is selected, LN will inform you when an order is not Completed, and it is past its latest finish date.