Select Data for Work Center Planning Board (tisfc1131m000)
Use this session to select the data that you want to plan with the graphical planning board.
After you have selected the data, click Continue to start the graphical planning board.
This process is independent, which means that you can leave the current session by clicking Close and continue with the graphical planning board. You can restart this session from the planning board:
- Select .
- Choose Selection.
Field Information
- Site
-
The site ID.
Note: Only visible if multisite functionality is active. - Remainder Start Date
-
The date you want to start the operation, or if the operation has already been started, the date when you want to resume the operation.
- Planning Board Group
- Description
-
Description of the planning board.
- Message When Order is Late
-
If this check box is selected, LN will inform you when an order is later than the delivery date and time.
- Skip Operation Having Remaining Production Time = 0
-
If this check box is selected, LN does not show completed operations on the planning board. Operations are completed when there is no production time remaining.
- Remainder Start Date
-
The date you want to start the operation, or if the operation has already been started, the date when you want to resume the operation.