Select Data for Planning Board (tisfc1125m000)
Use this session to select the production orders that must be displayed in the graphical planning board (JSC Gantt chart). You can simply select a range of production orders, but you can also use several criteria to select production orders, for example, production orders by PCS project, production start date, machine, or work center.
Carry out the following steps:
- Select the data that you want to view in the graphical planning board.
- Click . The graphical planning board is started.
In the planning board, you can choose how to view the production orders. For more information, refer to Planboard JSC (tisfc1126m000).
Field Information
- Site
-
The site ID.
Note: Only visible if multisite functionality is active. - Production Order
- Project (PCS)
- Production Start Date and Time
-
The date that the production order is started.
- Planned Delivery Date
-
The date that the production order items are finished according to the planning.
- Order Status
- Work Center
- Machine
- Remainder Start Date
-
The date on which the rest of the production is planned to start.
- Item From
- Skip operations having Remaining Production Time = 0
-
If this check box is selected, finished operations are not displayed in the planning board.
- Skip operations with status Completed
-
If this check box is selected, operations with the Completed status are not displayed in the planning board.
- Read Only
-
If this check box is selected, you will not be able to move operations around with the mouse in the planning board to change the operations' planning data. However, you will be able to double-click the operation blocks in the planning board, so that the appropriate session is started in which you can change planning data.
- Grid Size
-
If you are replanning operations in the graphical planning board, you can define the step size (in minutes) to drag and drop an operation. For example, if the Grid Size field is 30 minutes, you can move an operation with steps of 30 minutes. The start time of your operation can then be 12.30, 13.00, 13.30, etcetera.
Note: If your grid size is 1 or 2 minutes, and you increase it, for example, to 15 or 30 minutes, the sensivity of the planning board is decreased. A larger step size prevents you from accidently moving an operation by only touching the operation with the mouse. - Activity Description
-
The description on the activity bars can be:
Allowed values
- Order and Operation
- Main Item
- Operated Item