Print Material Shortages by Production Order (tisfc0419m000)
Use this session to check whether the material that is required for production orders is available in time.
Report
The report displays the following symbols:
* | Indicates a material shortage. |
! | Indicates that the material availability depends on the execution of other orders. If those orders are delayed, a material shortage can occur. |
Field Information
- Selection Range
-
- Selection
-
Select how the production orders are chosen.
Allowed values
- By Order
- By Group
- Site
-
- Production Order Group
- Production Order
- Project (PCS)
- Production Start Date and Time
-
The start date and time of the production order.
- Planner
- Shop Floor Planner
- Options
-
- Check
-
Determines what kind of check this session performs.
Allowed values
- On Hand
-
Requirements for the component from anther production order is taken into account only if:
- The production order has already been released.
- The production order has not been released, but is contained in the selection range specified under Selection.
- Planned Available
-
LN checks the projected available quantity, based on all planned inventory transactions, including scheduled receipts from all purchase orders and production orders. This check is not multilevel.
Note: This check is not multilevel. LN does not check whether materials supplied by other production orders are delayed because of material shortages for those production orders. - Multilevel
-
LN checks the projected available quantity.
If a material must be supplied by a production order, LN also checks whether the materials for that production order will be available in time.
LN recursively checks the availability of lower-level materials. For more information, refer to Multilevel material shortage check.
- Scope
-
Determines from which warehouses LN takes the available inventory into account.
Allowed values
-
Current Warehouse Only
Take only the inventory in the warehouse of the material into account. The material's warehouse is displayed in the Warehouse field in the Bill of Material (tibom1110m000) session. -
Planned Warehouses in Planning Cluster
Take the inventory into account in all warehouses in the same cluster as the material's warehouse. In general, nearby warehouses belong to the same cluster. However, LN excludes the warehouses for which the Include in Enterprise Planning check box in the Warehouses (tcmcs0503m000) session is cleared. -
All Warehouses in Planning Cluster
Take the inventory into account in all warehouses in the same cluster as the material's warehouse, regardless of the setting of the Include in Enterprise Planning check box in the Warehouses (tcmcs0503m000) session.
If the Check field is Multilevel, this field is Planned Warehouses in Planning Cluster and cannot be changed.
-
- Skip Blocked Inventory
-
If this check box is selected, LN does not take the inventory that is blocked into account for analyzing the production orders' material supply. Inventory can be blocked for inspection or for other reasons. Select this check box if you expect the material quality to be poor.
If the Check field is Multilevel, this check box is automatically set the same as the Inventory In Inspection Available for Planning check box in the Inventory Handling Parameters (whinh0100m000) session and cannot be changed.
- Critical Items Only
-
If this check box is selected, LN checks only the materials for which the Critical for Inventory check box in the Item - Production (tiipd0101m000) session is selected.
Note: If you check multilevel, and a material that is not critical has lower-level materials that are critical, LN will check these lower-level materials.
-
-
Select the type of orders to be printed.
Allowed values
- All Orders
- Orders with Shortage
- Orders without Shortage