Print Production Order Documents (tisfc0408m000)

Use this session to print production order documents such as routing sheets, material sheets and subcontracting notes.

Field Information

Selection Range
Selection

Select how the production orders are chosen.

Allowed values

  • By Order
  • By Group
Site

site

Project (PCS)

project

Production Order

production order

Operation

operation

Production Date

This field refers to the production start date and time field in the Production Orders (tisfc0501m000) session.

Item Group

item group

Warehouse

warehouse

Planner

The logon code of the employee who plans plan items.

Shop Floor Planner

The employee responsible for planning on the job shop.

Product Line

product line

Product Class

product class

Selection Code

selection code

Group Selection
Production Order Group

Enter the production order group for which you want to print documents.

Options
Print Options
Production Date range applies to Operation Start Date

If this check box is selected, the Remainder Start Date of operations determines for which production orders documents are printed. Order documents are only printed for production orders with uncompleted operations whose earliest Remainder Start Date is within the Production Date range (defined on the first tab). Operation notes, material issue notes, and subcontracting notes are only printed for operations which have a Remainder Start Date within the Production Date range.

If this check box is cleared, the Production Start Date of the production order determines whether order documents are printed. Order documents are printed when the Production Start Date of the production order is within the Production Date range.

Print Specification

If this check box is selected, the specifications are printed on the report.

Orders Sorted By
Orders Sorted By

The way the order are sorted for which you want to print the production order documents.

Allowed values

  • Order Number
  • Project (PCS) and Order
Documents Sorted By

The order that production order documents are printed.

Allowed values

  • Documents by Order
  • Orders by Document
Infor SCM Scheduler
Documents
Documents to be Printed
Order Covering Note

If this check box is selected, the covering note is printed.

Routing Sheet

If this check box is selected, the routing sheet is printed.

Operation Note

If this check box is selected, the operation note is printed.

Collective Sawing List

If this check box is selected, the collective sawing list will be printed.

Cutting List

If this check box is selected, the cutting list is printed.

Collective Cutting List

If this check box is selected, the collective cutting list will be printed.

Material List

If this check box is selected, the material list is printed.

Receipt Note

If this check box is selected, the receipt note is printed.

Material Issue Note

If this check box is selected, the material issue note is printed.

Inspection Note

If this check box is selected, the inspection note is printed.

Note: This is the default setting.

Subcontracting Note

If this check box is selected, the subcontracting note is printed.

Collective Material Issue Note

If this check box is selected, the reports for the entire order group are combined.

If this check box is cleared, each production order produces a report on a separate page.

Checklist

If this check box is selected, the checklist is printed.

Serial Number List

If this check box is selected, the serial numbers generated for the items specified in the production order are printed.

Sawing List

If this check box is selected, the sawing list is printed.

Include Microrouting on Routing Sheet

If this check box is selected, the information you linked to the microrouting is printed on the routing sheet.

Order Distribution

If this check box is selected, the order distribution report is printed.