Work Center Plan Groups (tisch0140m000)

Use this session to view and manage work center plan groups used for scheduling production.

Work center plan groups determine the scope of the planning the scheduler will generate.
Note: Work center plan groups are only active if scheduling is active for the company and site.

Field Information

Site

The site for which the work center plan group is defined.

Plan Group

The plan group ID.

Scheduler Controlled

If this check box is selected, the selected plan group is schedule controlled.

Note: If the selected plan group has a machine capacity group that is changeover critical, this parameter cannot be cleared.
Time Fence

The date until which the production orders are frozen. The time fence is expressed as a number of working days.

You can set the time fence for the plan group in the Scheduler Settings (tisch0140m100) session. You can start the session from the menu.

Note: You can only set scheduler settings for plan groups which are scheduler controlled.
Horizon

The time period for which LN schedules the production orders. The horizon is expressed in a number of working days.

Production orders with a start date after the horizon date are not included in the production schedule.