Work Cell Costs (tirpt7601m000)

Use this session to view the calculations for a selected cost document.

You can view both either the final calculations of closed documents, or interim calculations of open cost documents.

Field Information

Site

The site ID.

Note: Only visible if multisite functionality is active.

Work Cell

The work cell for which the cost document is maintained.

Cost Document

The document code that determines the material issued and end item receipts for repetitive production schedules in a specific work cell.

Start Date

The start date and time of the Cost Document.

End Date

The end date and time of the Cost Document.

Cost Document Status

The cost document status.

Allowed values

Open

Costs can be added to the cost document.

Closed

Costs can no longer be added to the cost document.

Initial

The cost document has been generated, but no costs have been added.