Work Cell - OEE (tirpt4540m000)

Use this session to view the overall equipment effectiveness of one or more work cell and shift.

Field Information

Site

The site ID.

Note: Only visible if multisite functionality is active.

Work Cell

work cell

Shift Start Date

The selected shift start date.

Shift

The shift ID.

Availability (%)

The percentage of time the selected work cell is available for production.

Availability% = Net Operating Time / Net Available Time * 100
Performance (%)

The percentage of time the selected work cell is operational.

Performance% = Ideal Operating Time/ Net Operating Time * 100
Quality (%)

The percentage of product manufactured correctly during operating time.

Quality% = (Ideal Operating Time - Lost Operating Time)/ Ideal Operating Time * 100
OEE (%)

The overall equipment effectiveness of the work cell and shift.

Availability * Performance * Quality