Cancel Production Schedule Lines (tirpt4202m300)

Use this session to cancel Production Schedule Lines with the status Released.

Note: 
  • You can access this session only if the Repetitive Manufacturing (RPT) check box is selected in the Implemented Software Components (tccom0100s000) session.
  • You can use the Cancel Lines option from these sessions to access this sessions:
    • Work Cell Planning (tirpt4102m200)
    • Production Schedule Lines (tirpt4102m000)
    .
  • You can cancel the lines in the Production Schedule Lines (tirpt4102m000)session only if:
    • The Production Schedule Line status is Released.
    • The production warehouse order line status is Open or does not exist in the Production Warehouse Orders (timfc0101m000) session.
    • The production warehouse order line status is Planned in the Production Warehouse Orders (timfc0101m000) session and the Backflush check box is selected for the line.
    • The Tool Requirement Status is Unallocated or Not Applicable.
    .
  • The locked production schedule lines with the status Released can be canceled in the Production Schedule Lines (tirpt4102m000) session using the Cancel Lines option from the Actions menu.
  • The production schedule lines can be archived and/or deleted using the options in the Archive/Delete Production Schedules (tirpt4201m100) session.
    Note: Production Schedule Lines with the status Canceled can be archived or deleted using Production Schedule Lines (tirpt4102m000) session.

Field Information

Selection Range
Site
The code of the site linked to the selected company.
Note: 
  • This field is displayed only if the Sites field is Active in the Implemented Software Components (tccom0100s000) session.
  • The application defaults this value from the Production User Profiles (timfc0120m000) session, if the site is specified for the currently logged in user.
  • This field is enabled only if the All Sites allowed check box is selected in the Production User Profiles (timfc0120m000) session. You can select the preferred Site to cancel the production schedule lines.
Work Cell
The code of the work cell.
Note: 
  • The work cell field is mandatory to select and cancel production schedule lines.
  • The linked schedule line materials are automatically deleted from the Schedule Line Materials (tirpt4121m000) session after canceling the production schedule lines.
Production Schedule
The From and To fields define a range of production schedules.
Lines
The From and To fields define a range of production schedule lines with status Released.
Note: 
  • You can select the View All Lines option from the Views menu to display all production schedule lines including canceled ones.
  • Production Schedule Lines with the status Active are included in the skipped records because Production has already started.
  • You can check the unsuccessful cancellation warning message using LN UI MessageViewer.