Shift - Materials (tirpt4121m100)
Use this session to maintain material for schedule lines that have the end item reported as complete for a specific work cell and shift.
- To return the already issued materials, select the material line and decrease the material quantity.
- To issue more materials, select the material line and increase the material quantity.
Field Information
- Work Cell
-
The work cell code.
- Shift
-
The shift name.
- Product
-
The item that is produced.
- Schedule
-
The ID of the schedule.
- Line
-
The schedule line number.
- Status
-
The shift status.
Allowed values
- Free
-
Run schedule is controlled by the planning engine.
- Firm
-
- The production schedule lines with the status Firm can be replanned only by using the Move Schedule (tirpt4202m000) session and not by the Enterprise Planning or other planning engines.
- Production Schedule Lines with a status of Firm can be locked from replanning or moving by planning engines such as Enterprise Planning.
- Released
-
Run schedule complete, changes can only be made manually.
- Active
-
Production run schedule is being implemented.
- Production Completed
-
All schedule lines for the production run were completed, but the run has not been closed.
- Completed
-
All schedule lines for the production run were completed, and all completed products were delivered into inventory. You can still account hours and issue materials for the run schedule.
- Closed
-
The run schedule was completed, changes can no longer be made.
- Position
-
The position number of the material line.
- Material
-
The component item that is part of the manufactured item (the standard material) used in the specified shift.
- Unit
-
The inventory unit for the material.
- Net Quantity
-
The net quantity of the material needed for the production schedule line.
- Actual Quantity
-
The actual quantity issued from inventory.
- Scrap Percentage
- Estimated Quantity
-
The estimated quantity of material required. This value is based on the Net Quantity specified for the particular production schedule line.
- To Issue
-
The material quantity that must be issued. It is defined with the following formula:
Estimated - Backflushed
- Point of Usage
-
The shop floor warehouse linked to the work station that contains the material for the production of the repetitive item.
- Backflush
-
If this check box is selected, the schedule line materials are backflushed.