Schedule Line Work Stations (tirpt4111m000)

Use this session to view the work stations linked to the work cell of the production schedule line.

Note: 
  • The Report on Work Stations check box in the Repetitive Manufacturing Parameters (tirpt0100m000) session must be selected to use this session.
  • The schedule line must have the status Released.
  • The Quarantine Inventory check box in the Inventory Handling Parameters (whinh0100m000) session must be selected to use the quarantine options in this session.

Field Information

Production Schedule

The production schedule ID.

Schedule Position

The line position in the schedule.

Allowed values

Free

Run schedule is controlled by the planning engine.

Firm
  • The production schedule lines with the status Firm can be replanned only by using the Move Schedule (tirpt4202m000) session and not by the Enterprise Planning or other planning engines.
  • Production Schedule Lines with a status of Firm can be locked from replanning or moving by planning engines such as Enterprise Planning.
Released

Run schedule complete, changes can only be made manually.

Active

Production run schedule is being implemented.

Production Completed

All schedule lines for the production run were completed, but the run has not been closed.

Completed

All schedule lines for the production run were completed, and all completed products were delivered into inventory. You can still account hours and issue materials for the run schedule.

Closed

The run schedule was completed, changes can no longer be made.

End Item

product

Work Cell

work cell

Status

Production line status.

Allowed values

Free

Run schedule is controlled by the planning engine.

Firm
  • The production schedule lines with the status Firm can be replanned only by using the Move Schedule (tirpt4202m000) session and not by the Enterprise Planning or other planning engines.
  • Production Schedule Lines with a status of Firm can be locked from replanning or moving by planning engines such as Enterprise Planning.
Released

Run schedule complete, changes can only be made manually.

Active

Production run schedule is being implemented.

Production Completed

All schedule lines for the production run were completed, but the run has not been closed.

Completed

All schedule lines for the production run were completed, and all completed products were delivered into inventory. You can still account hours and issue materials for the run schedule.

Closed

The run schedule was completed, changes can no longer be made.

Scheduled Start Date

The date and time manufacture on the schedule line starts.

Work Station

The work station that is part of the work cell.

Station Position

The position of the work station in the work cell structure.

Work Station Is Count Point

If this check box is selected, the work station is a count point.

Work Station is Inspection Point

If this check box is selected, the work station is an inspection point.

Note: Only applicable if the Report on Work Stations check box in the Production Model (tirpt2100m100) session is selected for the product model.
Quantity Rejected
The total quantity that is rejected during production for the schedule line.