Work Cell Planning (tirpt4102m210)
Use this session to manage production planning on work cell level.
Field Information
- Work Cell
- Planned Start
-
The planned start date for the production of the item.
- Schedule
-
The production schedule ID.
- Line
-
The line position in the schedule.
- Product
- Quantity Ordered
-
The quantity of item
- Duration [Hrs]
-
The production time for the specified item.
- Quantity to Backflush
-
The quantity to backflush.
- Quantity Backflushed
-
The quantity of end product included in the total run quantity for which materials and or hours have been posted using backflushing.
Note: Quantities that are backflushed, are automatically posted when the run is completed. - Production Finish Date
-
The date on which the production order is completed.
- Actual Production Start Date
-
The date production started.
- Actual Production Finish Date
-
The date production finished.
- Origin
-
The origin of the production run.
Allowed values
- Planning
-
The production run is scheduled using Enterprise Planning .
- Manual
-
The production run is scheduled manually.
- Status
-
Production line status.
Allowed values
- Free
-
Run schedule is controlled by the planning engine.
- Firm
-
- The production schedule lines with the status Firm can be replanned only by using the Move Schedule (tirpt4202m000) session and not by the Enterprise Planning or other planning engines.
- Production Schedule Lines with a status of Firm can be locked from replanning or moving by planning engines such as Enterprise Planning.
- Released
-
Run schedule complete, changes can only be made manually.
- Active
-
Production run schedule is being implemented.
- Production Completed
-
All schedule lines for the production run were completed, but the run has not been closed.
- Completed
-
All schedule lines for the production run were completed, and all completed products were delivered into inventory. You can still account hours and issue materials for the run schedule.
- Closed
-
The run schedule was completed, changes can no longer be made.
- Warehousing Order
- Quantity Completed
-
The quantity of product reported completed.
- Original Start Date
-
The earliest date materials to manufacture the item are available.
- Original Finish Date
-
The earliest date the planned quantity can be completed.