Production Schedule Totals (tirpt1501s000)
Use this session to display production schedule totals. The totals are applicable to the item or the area schedule, depending on the view of the Production Schedules (tirpt1500m000) session or the Report Production Orders Completed from Production Schedule (tirpt1502m000) session from which this session is started.
Field Information
- Scheduled Prod Ord
-
The sum of the ordered quantities for JSC orders.
- Scheduled till DayEnd
-
The sum of the quantity ordered of all orders that have a delivery date before or on the current date.
- Scheduled RRP/INA
-
The sum of ordered quantities for RRP orders and INA orders.
- Sched. till Day Start
-
The sum of the quantity ordered of all orders that have a delivery date before the current date.
- Total Scheduled
-
The sum of the ordered quantities for JSC, RRP, and INA orders.
- Scheduled Today
-
The quantity ordered that is scheduled on the current date. This quantity equals the quantity in the Scheduled till DayEnd field minus the quantity in the Sched. till Day Start field.
- Quantity Delivered
-
The sum of the quantity delivered for JSC orders.
- Delivered Today
-
The sum of the quantities delivered for the JSC orders that have a delivery date equal to the current date.
- Quantity Scrapped
-
The sum of the quantity rejected for the JSC orders.
- Rejected Today
-
The sum of the quantities rejected for the JSC orders that have a delivery date equal to the current date.
- Quantity Remaining
-
The quantity that must still be delivered. This quantity equals the quantity in the Total Scheduled field, minus the quantity in the Quantity Scrapped field, minus the quantity in the Quantity Delivered field.
- Remaining Today
-
The quantity that must still be delivered on the current date, which equals the sum of the quantity in the Total Scheduled field and the quantity in the Delivered Today field, minus the quantity in the Rejected Today field.