Work Cell (tirpt0640m000)

Use this session to generate and manage work cells.

Field Information

Site

The site ID.

Note: Only visible if multisite functionality is active.

Work Cell

The work cell ID.

Planning and Scheduling
Work Cell Plan Group

The ID of the plan group to which the work cell is assigned.

Constraint Resource

If this check box is selected, the selected resource has constraints.

Note: Only applicable if the Constraint Planning Implemented parameter in the Planning Parameters (cprpd0100m000) session is selected.
Costing
Available Labor Resources

The number of operators required for the work cell.

Operation Rate Code
The operation rate code refers to the rates that are used for the work cell.
Note: The application defaults the field value from the Production Settings by Site (timfc0180m000) session.
Enterprise Unit

enterprise unit

Finance Company

financial company

Operational Company

operational company

Address

address

Production Department

production department

Default Labor Resource

The employee number to which hours are posted in People by means of backflushing.

Work Cell Calendar

The calendar linked to the specified work cell.

If no calendar is specified, the production department calendar is used.

Actual Calendar

The calendar and availability type combination that is used by the work center manufacturing a production order.

Note: 
  • If a work center calendar is specified, the actual calendar equals the work center calendar. If no work center calendar is specified, the next applicable calendar is used such as that of the related Production Department.
  • You can see the level at which the actual calendar is defined in the Origin field.

Origin

The ID of the session where the actual calendar is defined.

Repair Cell

The ID of the repair cell linked to the work cell.

Labor Rate Code

The labor rate code assigned to the department.

Report on Work Stations

If this check box is selected, schedule lines are reported completed at work station and work cell levels.

If this check box is cleared, schedule lines are only reported completed on work cell level.

Note: Reporting completed is mandatory at work stations marked as count points.

Allowed values

Progress Reporting in Repetitive Manufacturing