Work Cell (tirpt0640m000)
Use this session to generate and manage work cells.
Field Information
- Site
-
The site ID.
Note: Only visible if multisite functionality is active. - Work Cell
-
The work cell ID.
- Planning and Scheduling
-
- Work Cell Plan Group
-
The ID of the plan group to which the work cell is assigned.
- Constraint Resource
-
If this check box is selected, the selected resource has constraints.
Note: Only applicable if the Constraint Planning Implemented parameter in the Planning Parameters (cprpd0100m000) session is selected.
- Costing
-
- Available Labor Resources
-
The number of operators required for the work cell.
- Operation Rate Code
- The operation rate code
refers to the rates that are used for the work cell.Note: The application defaults the field value from the Production Settings by Site (timfc0180m000) session.
- Enterprise Unit
- Finance Company
- Operational Company
- Address
- Production Department
- Default Labor Resource
-
The employee number to which hours are posted in People by means of backflushing.
- Work Cell Calendar
-
The calendar linked to the specified work cell.
If no calendar is specified, the production department calendar is used.
- Actual Calendar
-
The calendar and availability type combination that is used by the work center manufacturing a production order.
Note:- If a work center calendar is specified, the actual calendar equals the work center calendar. If no work center calendar is specified, the next applicable calendar is used such as that of the related Production Department.
- You can see the level at which the actual calendar is defined in the Origin field.
- Origin
-
The ID of the session where the actual calendar is defined.
- Repair Cell
-
The ID of the repair cell linked to the work cell.
- Labor Rate Code
-
The labor rate code assigned to the department.
- Report on Work Stations
-
If this check box is selected, schedule lines are reported completed at work station and work cell levels.
If this check box is cleared, schedule lines are only reported completed on work cell level.
Note: Reporting completed is mandatory at work stations marked as count points.Allowed values
Progress Reporting in Repetitive Manufacturing