Repetitive Settings History by Site (tirpt0181m000)
Use this session to view the history of the repetitive manufacturing settings for a specific site.
Field Information
- Site
-
- Site
- External
-
If this check box is selected, the planning cluster is linked to subcontractor sites or the planning cluster is used in planning for VMI Forecast.
This depends on the settings of these check boxes:
- Holds Subcontractor Sites
- Customer Site
- Address
- Logistic Company
- Repetitive
-
- Effective Date
-
The date and time the parameters were adjusted.
- Last Changed by
-
The code of the employee who made the last changes to the repetitive parameters.
- Text
-
If this check box is selected, additional text is present.
- .
-
- Use Global Repetitive Parameters
-
If this check box is selected, the global repetitive parameter data is used for the site. Consequently, changes to product data at company level are synchronized automatically to the site level.
- Repetitive Production Schedules
-
- Repetitive Production Schedules
-
If this check box is selected, repetitive production schedules are used to manufacture the product.
Allowed values
Repetitive Production Scheduling
- Production Model Series
-
The default series that is used to generate production model codes.
Allowed values
Production Model
- Series for Manual Schedule Creation
-
The default series used when manually generating production schedules in Repetitive Manufacturing .
- Series for Manual Schedule Creation
-
The series that is used by Enterprise Planning to generate production schedules in Repetitive Manufacturing .
- Series for Warehousing Orders
-
The series that is used to generate warehousing-order numbers.
- Series for Work Cell Cost Documents
-
The default series used for creating work cell cost documents.
- Work Cell Cost Document Duration
-
Specify the duration of the schedule line.
Note:The duration can be:
- Day
- Week
- 4 Weeks
- Month
- Generate Serial Numbers
-
Specify when the serial numbers for a schedule line are generated.
Allowed values
- Manually
- On Release
- Material Backflushing Method
-
The value of this field determines the degree of user interaction when backflushing is carried out.
Allowed values
- Automatic
- Manual
- Interactive
Performance aspects
The setting of this field could affect system performance and database growth. For more information, refer to Backflushing method.
- Automatic Work Cell Hours
-
If this check box is selected, automatic registration and booking of actual work cell hours is active.
- Work Cell Hours Method
-
The method by which the work cell hours are determined.
Allowed values
-
Register Work Cell Hours
Hours logged by the user. -
Backflushing Hours
A theoretical process time based on reported completed and rejected items.
-
- Backflushing without Warehouse Orders
-
If this check box is selected, materials are backflushed without warehouse orders to issue material inventory.
- Automatic Labor Hours
-
If this check box is selected, automatic registration and booking of actual labor hours is active. The Labor Hours hours in the Report Shift (tirpt4636m200) session are automatically copied and booked to the Actual Labor Hours in the Shift - Hours (tirpt4138m000) session.
Note: Labor hours do not have a method option and are always registered. - Progress Tolerance
-
The progress of the process variable in percentages.
- Report on Work Stations
-
If this check box is selected, schedule lines are reported completed at work station and work cell levels.
If this check box is cleared, schedule lines are only reported completed on work cell level.
Note: Reporting completed is mandatory at work stations marked as count points.Allowed values
Progress Reporting in Repetitive Manufacturing
- Work Station Machines
- The machine linked to a Work Station.
- Repair Process
-
If this check box is selected, items can be send for repair during manufacture.
- Multi-Product Production
-
If this check box is selected, use of production models for multiple end products is implemented.
- Scheduling Process
-
- Allow Offloading
-
If this check box is selected, offloading of planned runs to work cells with later need dates is possible.
Allowed values
Repetitive Production Scheduling
- Move and Swap Lines
-
If this check box is selected, you can move and swap lines within a run.
Allowed values
Repetitive Production Scheduling
- Move and Swap Runs
-
If this check box is selected, you can move and swap scheduled runs.
Allowed values
Repetitive Production Scheduling
- Offload Runs
-
If this check box is selected, selected runs are offloaded to other work cells.
Allowed values
Repetitive Production Scheduling