Job Shop Routing Operation (tirou4601m000)
Use this session to display routing operations.
This session displays data from the following sessions:
- Job Shop Routing Operation - Operation Steps (tirou4110m000)
- Routing Operation - Instructions (tirou4115m000)
- Job Shop Routing Operation - Skills (tirou4112m000)
- Job Shop Routing Operation - Tools (tirou4111m000)
- Job Shop Routing Operation - Process Variables (tirou4113m000)
Field Information
- Product
-
The product ID.
- Site
- Routing
- Revision
-
The routing revision to which the related routing operation applies.
- Status
-
The status of the routing.
Allowed values
- New
- Expired
- Approved
- Effective Date
-
The date the routing becomes effective.
- Routing Quantity
-
The quantity of product on which the cycle time is based.
- Standard Routing
- If this check box is selected, the operation sequence is linked to a standard routing for the selected item and site combination and may apply to several items. The Standard Routing Code field contains the standard routing code.
- Minimum Quantity
-
The minimal quantity of product for which the routing is used.
- Maximum Quantity
-
The maximal quantity of product for which this routing is used.
- Reference Operation Text
-
If this check box is selected, text is present related to the production order.
- Order Lead Time
- Operation Text
-
If this check box is selected, text is present related to the operation.
- Operation
-
The operation ID.
- Next Operation
-
If you defined a network routing, the operation that is specified in this field must be performed after the current operation.
Note: This field is visible if the Allow Parallel Operations in Routing check box in the Job Shop Master Data Parameters (tirou0100m000) session is selected.-
Regular routing
If you do not define a network routing, the Next field must be 0 (zero) for all routing operations. In that case, the operations are performed in order of operation number, for example, 10 - 15 - 20 - 40.
-
Network routing
If you define a network routing, the following conditions apply:
- Exactly one operation is the end operation. For the end operation, the Next field is 0 (zero).
- The operation number of the next operation must be greater than the number of the current operation. For example, operation 40 must not follow operation 50.
LN does not automatically check these conditions. To check whether the routing meets the conditions, on the appropriate menu, click .
When a production order is created, LN validates the routing and stops the process if the routing is incorrect.
-
- Standard Configuration
- If this check box is selected, the JSBOM line is part of the product's standard configuration.
- Subcontracting
- If this check box is selected, the operation is subcontracted.
- Reference Operation
-
The reference operation code.
- Reference Operation Machine Type
-
The code of the machine type the reference operation is specified for.
Note: You can specify the same reference operation for one or more machine types, sites or capacity groups. - Reference Operation Site
-
The site for which the reference operation is specified.
- Reference Operation Work Center
-
The code of the work center the reference operation is specified for.
- Machine Type
-
The sort of machine that is used during production.
- Work Center
- Work Center Site
-
The code of the site to which the work center belongs. Only for subcontracting work centers, that can deviate from the site of the routing.
- Fixed Setup Time
-
The sequence independent time required to set up or change over a machine in order to start running the machine.
- Setup Scrap
-
Unusable or rejects of intermediate products, for example, because of faulty components, or products lost in cutting and sawing operations.
The gross requirements and/or an operation's input quantity must be increased to account for anticipated scrap.
For an operation, you can define planned scrap as a fixed quantity (setup scrap), or as relative loss via discrete yield.
- Yield Type
-
Allowed values
- Continuous
-
The percentage of the product that is lost disappears completely. For example, product loss due to evaporation.
- Discrete
-
The percentage of the product that is lost appears as rejected components.
- Yield Percentage
- The yield output expressed as a percentage of its input.
In case opertaions are defined, yield need to be defined per operation.
- Exceptions Present
- If this check box is selected, this BOM line has exceptions linked to it. Exceptions are part of the unit effectivity concept.
- Setup Time
- Labor Resources for Setup
-
The number of employees needed for setup, expressed in fulltime equivalent.
- Cycle Time
- Labor Resources for Production
-
The number of employees needed, expressed in fulltime equivalent.
- Production Rate
-
The number of units for which the task can be performed per unit of time on a work center. The unit is per hour or per minute depending on the Production Rate Time Unit field in the Job Shop Master Data Parameters (tirou0100m000) session. The rate is derived from the cycle time as they are reciprocative.
If the Use Production Rates parameter in the Job Shop Master Data Parameters (tirou0100m000) session is selected, you can enter the production rate, and the cycle time will be derived.
- Number of Machines
-
The number of machines that are available for production on the work center.
- Setup Class Set
- The setup class set of the machine capacity group. The name of the set of setup classes and setup class states from the machine capacity group.
- Process Time
-
The process time is the time between completion of two separate units of production on a machine. If an operation is processed on two machines, and has a cycle time of 4 minutes, the process time will be 8 minutes.
- Queue Time
-
The queue time is used in lead time calculation. The queue time is expressed in days or hours. The days or hours must be interpreted as days and hours in the working time calendar that is linked to the work center.
If the Time Unit field is Days, LN rounds the entered values of the lead times to integer values.
- Wait Time
-
When LN calculates the start times and end times of planned orders based on the routing, LN considers the wait time. The wait time is expressed in days or hours. The days or hours do not relate to a calendar. The availability of time is considered as 24 hours a day, seven days a week.
If the Time Unit field is Days, LN rounds the entered values of the lead times to integer values.
The plan buffer created by the wait time enables you to build in a certain tolerance between successive operations, which makes it possible to shift operations in case planning must be adjusted.
Note: This field is not accessible if the Work Center Type field is Costing, Line Station or Buffer. - Move Time
-
If the Time Unit field is Days, LN rounds the entered values of the lead times to integer values.
- Report Product
-
If this check box is selected, the operation is a count point.
- Standard Configuration
- If this check box is selected, the JSBOM line is part of the product's standard configuration.
- Subassembly
- Use Transfer Batch
-
If this check box is selected, you can start work on a routing operation before the preceding operation is finished.
- Transfer Batch Quantity
-
The quantity of product that must be finished to start the next routing operation if the Use Transfer Batch check box is selected.
- Fixed Duration
- .
-
- DMS on Completion
-
If this check box is selected, direct material supply (DMS) planning will be run when the operation is reported complete.
- Report Product
-
Specify how production is reported:
Allowed values
-
Manual
Reporting is done manually in the Machine Work List (tisfc4600m000) session for machine operations and in the Report Operations Completed (tisfc0130m000) session for other operations. -
Automatic
Reporting is done by the completion of another operation.
-
- Report Machine Hours
-
Specify how machine hours are reported:
Allowed values
-
Backflush
This is an automatic calculation based on reported quantities. -
By Machine Group
Reporting is done by machine in the Report Operations Completed (tisfc0130m000) session.
-
- Report Labor Hours
-
Specify how hours are reported:
Allowed values
-
Backflush
This is an automatic calculation based on reported quantities. -
By Machine Group
Reporting is done by machine in the Report Operations Completed (tisfc0130m000) session.
-
- .
-
- Subcontracting with Material Flow
-
If this check box is selected, only subcontracting with material flow is used to produce the item.
- Selection Method
-
The method by which the subcontractor is selected for the operation.
Allowed values
- Planning
- Requisition
- Manual
- Not Applicable
- Subassembly
-
The subassembly that is part of the subcontracted operation.
- Subassembly Warehouse
-
The warehouse from which the subassembly is sent or in which the subassembly is received.
- Kanban
-
- Container
- Container Method
-
The shipment method how to handle items in the container. For instance, stack should be less than 10 tiers high.
- Container Quantity
-
The quantity of items stacked in the container.
- Number of Kanbans
-
The number of kanbans that is used in the pull system.
- Description on Kanban
-
The description of the inter-operation kanban that serves as an identification for the kanban.
- Activity
-
The project activity defined in the Activities (tipcs4101m000) session to which the operation is related.
Note: Only applies to customized items.