Reassign Job Shop Operations (tirou4201m100)
Use this session to perform a change for a series of Job Shop Routing Operations. You can assign the operation to another:
- Work center,
- Machine capacity group,
- Reference operation.
Field Information
- Change Note
-
- Change Note Selection
-
Indicate that the change must be performed on a new change note.
Allowed values
- New
- A new change number is generated.
- Add to Note
- The change is added to an existing change note.
- Not Applicable
- Change Note
- The code of the change note.
- Reason
- The reason for performing the change.
- New Revision
-
- Effective Date
- The date and time from when the change is effective.
- Target Routing
-
- Site
- The site ID.
- Work Center
- The code of the work center at which the job shop routing is performed.
- Machine Type
- The machine capacity group is defined by
the work centre and the machine type.Note:
- You must specify this value if the Machine Capacity Groups check box is selected in the Work Center (tirou0601m000) session.
- The combination of Site, Work Center, and Machine Type must exist for the combination in the Machine Capacity Groups.
- Reference Operation
- The code of the reference operation. The Reference Operation must be applicable for the given specified combination of Site, Work Center, and Machine Type.
- Routing Code
- The routing code. Note: The value in this field can be defined only if the Work Center and the Reference Operation are specified.
- New Machine Capacity Group
-
- New Reference Operation
-
- Reference Operation
- The code of the reference operation. The Reference Operation must be applicable for the given Site, Work Center, and Machine Type.
- Options
-
- Approve New Revision
- If this check box is selected, the new revision is approved.
- Simulate
- If this check box is selected, the change is
not processed, but a report shows the revisions that are to be changed.Note: By default, this check box is selected.
- Print Process Report
- If this check box is selected, a report is