Use this session to calculate routings, based on operation lead times, for job shop routings for which the routing lead time is neither calculated or set.

Field Information

Site

The site for which the routing lead time is calculated.

From

The range of products for which the routing lead time is calculated.

Routing

The range of routings for which the lead time is calculated.

Revision

The product revision for which the routing lead time is calculated.

Status

The status of the routing for which the lead time is calculated.

Allowed values

  • New

    The routing was generated but has not yet been approved.
  • Approved

    The routing is approved and is in use.
  • Expired

    The routing has expired and can no longer be used.
Automatic

If this check box is selected, lead times are only calculated with routings with the lead time calculation method Automatic.

Manual with zero Lead Time

If this check box is selected, lead times are only calculated for routings with the lead time calculation method set to Manual or zero lead time.

Simulation

If this check box is selected, the routing lead times calculation is simulated and no changes are made.

Print Report

If this check box is selected, a report is printed once the lead time calculation is completed.