Reference Operations (tirou4150m000)
Use this session to view reference operations.
Field Information
- Reference Operation
-
The reference operation ID.
- Machine Type
-
The type of machine on which the reference operation is performed.
- Site
-
The site for which the reference operations are defined.
- Work Center
- Number of Machines
-
The number of machines used during production.
- Labor Resources for Production (FTE)
-
The number of employees needed, expressed in full-time equivalent.
- Routing Quantity
-
The quantity of product on which the cycle time is based.
- Setup Time
-
The time required for setting up or changing over a machine before you can start production again. Setup time can vary in duration depending on the machine and the operations performed.
- Cycle Time
- Production Rate
-
The number of units for which the task can be performed per unit of time on a work center. The unit can be per hour or per minute, depending on the Production Rate Time Unit field in the Job Shop Master Data Parameters (tirou0100m000) session. The rate is derived from the cycle time.
- Process Time
-
The time between completion of two separate units of production on a machine. For example, if an operation is processed on two machines, and has a cycle time of 4 minutes, the process time would be 8 minutes.
- Use Transfer Batch
-
If this check box is selected, you can stat work on a routing operation before the preceding operation is finished.
- Transfer Batch Quantity
-
The quantity of product that must be finished to start the next routing operation if the Use Transfer Batch check box is selected.
- Labor Resources for Setup (FTE)
-
The number of employees needed for setup, expressed in full-time equivalent.
- Fixed Setup Time
-
The sequence independent time required to set up or change over a machine in order to start running the machine.
- Fixed Duration
- Operation Rate Code
- Reference Operation Text
-
If this check box is selected, text related to the reference operation is present.