Capacity Load Table (tipcs4131m000)

Use this session to maintain the capacity-load table (CLT) for the rough capacity-requirements planning, by project. This is done on a capacity load table graph.

Field Information

Table

The code of the capacity load table, which indicates how to plan the global capacity in relation to the activity's duration.

Relative Activity Duration

Enter the cumulative percentage of the activity duration.

Relative Capacity Requirement

Enter the cumulative percentage of the estimated capacity with respect to the cumulative percentage of the activity duration.