Standard Cost by Project (tipcs3560m000)

Use this session to display the standard cost by project.

Note: If you have started this session by zooming, you can only find and select a record.

Field Information

Project

project

Project Type

This field indicates whether the project is a main project, a subproject, a single-level project or a budget.

Currency

The currency in which amounts are expressed.

Project Status

Indicates the project progress.

Cost Component

User-defined category for costs used to break down the product's standard cost. The costs are allocated to the cost component.

Budgeted Amount Variable

The variable part of the budgeted costs which have been posted to the relevant cost component, when the estimated cost is being calculated for the project. These costs are operation costs, material costs, etc.

Note: During the standard cost calculation for the project, the budgeted costs are loaded directly from the budget calculation.
Budgeted Amount Total

The budgeted costs which have been posted to the relevant cost component, when the estimated cost is being calculated for the project. These costs are operation costs, material costs, and so on.

Note: During the standard cost calculation for the project, the budgeted costs are loaded directly from the budget calculation.
Estimated Amount Variable

The cost which is posted to the relevant cost component for estimated operation costs, material costs, etc., during the standard cost calculation for a budget.

Estimated Amount Total

The cost which is posted to the relevant cost component for estimated operation costs, material costs, etc., during the standard cost calculation for a budget.

Actual Amount Total

The amount that you entered as actual costs for the acquisition of the customized item. These costs are posted to the relevant cost component, when LN calculates the actual standard cost for the item.

Cost Component Type

Defines the elements that make up the standard cost and the valuation price. Cost component types indicate the type of costs that must be posted to a cost component.

Budgeted Number of Units

The budgeted number of product units, not to be confused with units as yards and kilograms.

Estimated Number of Units

The estimated number of product units, not to be confused with units as yard and kilograms.

Actual Number of Units

Actual number of product units, not be confused with units as yards and kilograms.