Print Project Work-in-Process (tipcs3480m000)

Use this session to print the value of work-in-process (WIP) of a project.

Field Information

Print WIP Value on Calculation Office Only

If this check box is selected, LN only prints the WIP of the calculation office.

If this check box is cleared, LN prints all WIP.

Suppress Zero WIP Values

If this check box is selected, LN does not print zero WIP values.

Include Interim COS and Revenue

If this check box is selected, interim Cost of Goods Sold (COGS), interim revenue, and interim results are included in the report (if present for the PCS project), which results in a WIP balance.

Aggregation Level

Specify the level of detail.

Project

project

Sold-to Business Partner

sold-to business partner

Department

department

Warehouse

warehouse

WIP Analysis Date

LN prints the WIP value of the project until this date. So, WIP transactions after the entered date are not taken into consideration.