Print Project Work-in-Process (tipcs3480m000)
Use this session to print the value of work-in-process (WIP) of a project.
Field Information
- Print WIP Value on Calculation Office Only
-
If this check box is selected, LN only prints the WIP of the calculation office.
If this check box is cleared, LN prints all WIP.
- Suppress Zero WIP Values
-
If this check box is selected, LN does not print zero WIP values.
- Include Interim COS and Revenue
-
If this check box is selected, interim Cost of Goods Sold (COGS), interim revenue, and interim results are included in the report (if present for the PCS project), which results in a WIP balance.
- Aggregation Level
-
Specify the level of detail.
- Project
- Sold-to Business Partner
- Department
- Warehouse
- WIP Analysis Date
-
LN prints the WIP value of the project until this date. So, WIP transactions after the entered date are not taken into consideration.
- Currency for details
-
Specify the type of currency in which the report is printed.
- Currency for totals
-
The currency in which the report is printed.