Print Standard Cost by Project (tipcs3460m000)
Use this session to print the standard cost by project. For each project, you can print the budgeted standard cost, the estimated cost, and the actual standard cost.
You can also print:
- The differences between the budgeted standard cost, estimated standard cost, and the actual standard cost.
- Sales revenues.
The budgeted, estimated and actual standard cost data are calculated by means of the Calculate Standard Costs by Project (tipcs3250m000) session.
Field Information
- Project
- Search Key
- Project Status
-
The current progress of the project.
- Project Employee
-
The person that is in charge of the execution of the project.
- Start Date
-
The date the project is started.
- Completion Date
- Sold-to Business Partner
- Currency for details
-
The type of currency in which the report is printed.
- Currency for totals
-
The currency in which the report is printed.
- Include Fixed Costs in Standard Cost
-
If this check box is selected, the fixed costs are included in the standard cost and printed as well.
- Print Project when No Standard Cost Is Present
-
If this check box is cleared, only project data of projects is printed for which a standard cost is calculated.
- Include Commitments
-
If this check box is selected, the commitment amounts per cost component are included in the report. The total amounts include actual costs and commitment amount.
Note: The commitment amount is the value of the existing purchase orders that are still due to receive. - Report (Project/Project - Cost type)
-
You can chose to group data on report by:
Allowed values
- Project
- Project - Cost Type
- Comparison Between
-
You can chose to print a comparison report. This option is only available when grouping By Project and By Cost Type is required.
- Comparison Between
-
Indicate which comparison will be printed:
Allowed values
- Budget and Estimated Costs
- Budget and Actual Costs