Copy Customized Product Structure to Standard Structure (tipcs2232m000)
To copy the product structure of a customized item to a standard item.
Field Information
- Customized Item
-
Note:
- Standard items are expressed in an item code.
- Segmented items consist of a project code segment and an item base segment (the item code of the customized item). The segments an item can consist of are defined in the Item Code Segmentation (tcibd0500m000) session.
- Copy only components valid for Effectivity Unit
- Standard Item
-
Note:
- Standard items are expressed in an item code.
- Segmented items consist of a project code segment and an item base segment (the item code of the customized item). The segments an item can consist of are defined in the Item Code Segmentation (tcibd0500m000) session.
- Target Routing Code
-
Enter the code of the standard routing to which you want to copy the customized product structure.
- Copy Product Structure
-
In this field you can choose to copy the entire product structure or only its first level, or to make the copying process interactive.
- Reference Date
-
The date in this field determines that only those parts of the project structure are copied that are valid on the date specified.
- Copy E-Item Relationships
-
If this check box is selected, the E-item relationships are copied as well.
- Copy all components and all effectivity statements
-
If this check box is selected, unit effectivity is copied from a customized product structure to a standard structure. You can fill in the unit for which you want to copy unit effectivity. Exceptions are copied for routings and routing operations that fulfill the date effectivity conditions.
- Alternative Material
-
If this check box is selected, the alternative materials of the BOM components are copied as well. If this check box is cleared, the copying process ignores the alternative materials.
- Use Up Material
-
If this check box is selected, the use-up materials of the BOM components are copied as well. If this check box is cleared, the copying process ignores the use-up materials.
- New Item Codes for Existing Standard Components
-
If this check box is selected, LN generates new item codes for existing standard components.
- Approve Conversion Factors
-
If this check box is selected, LN copies the conversion factors to the target item, and then directly approves the conversion factors.
If this check box is cleared, LN copies the conversion factors to the target item. However, use the Conversion Factors (tcibd0103m000) session to manually approve the conversion factors.
- Copy to Standard Item Configuration
-
If this check box is selected, the customized item or the generic item product structure is copied to the specified standard item configuration.
Note:The product structure can only be copied to the specified standard item configuration when the product variant is not active in Order Management . If active supply orders for the product structure are present, they will lose relation with the sales order/quotation when the product structure is regenerated.
This field is only enabled if you select the Use Standard Item for Configuration check box in Product Configuration Parameters (tipcf0100m000) session.
If a customized structure is copied to a standard structure, the Customized check box is cleared on the standard structure.