Processed Production Bill of Material (timfc3650m100)
Use this session to view the created production bill of material (PBOM) revision including the list of materials.
- The Engineering Revisions check box is selected in the Implemented Software Components (tccom0100s000) session.
- The Job Shop by Site field is set to Active in the Implemented Software Components (tccom0100s000) session.
- The Originating App field is set to PLM (Internal) or PLM (external) in the Item Base Data Parameters (tcibd9199m000) session.
Tabs
- Materials
Refers to the Processed Production Bill of Material Lines (timfc3160m100) session. On this tab, you can view all the received material lines of the created production bill of material revision.
Field Information
- Product
- The code of the product associated with the processed production bill of material that is received from PLM.
- Revision
- The revision of the production bill of material received from PLM.
- Status
- The status of the processed production bill of
material received from PLM.
Allowed values
- New
- Approved
- Expired
- Bill of Material
-
- BOM Quantity
- The BOM quantity of the received production bill of material.
- Unit
- The unit in which the BOM quantity is expressed.
- Use BOM Units
- If this check box is selected, LN uses
the BOM units for the processed production bill of material.Note: This field is applicable only if the BOM Units on Material Lines check box is selected in the Product Engineering Parameters (timfc0100m000) session.
- Revision
-
- Effective Date
- The date and time from which the processed production bill of material is valid.
- Expiry Date
- The date and time up to which the processed production bill of material is valid.
- Text
- If this check box is selected, the text related to the processed production bill of material exists.
- Source
-
- Source
- The source of the received production bill
of material.
Allowed values
- Manual
-
The P-BOM is defined in the Production Bills of Material (timfc3100m000) session.
- Production Bill of Material
-
The P-BOM revision was generated from an existing production bill of material.
- Engineering Bill of Material
-
The P-BOM is generated from an engineering bill of material.
Note: If the P-BOM is generated from an E-BOM, the Source Engineering Item and Source Revision fields are filled. - PLM
-
The P-BOM is generated from data imported from PLM.
- Configurator (PCF)
-
The P-BOM is generated from data imported from the PCF configurator.
- Configurator
-
The P-BOM is generated from data imported from Infor Configurator.
- Job Shop Bill of Material
-
The P-BOM was generated from a job shop bill of material.
- Not Specified
Note: By default, this field is set to PLM. - Source Item
- The code of the source item for which the production bill of material is defined.
- Source Revision
- The revision of the source item for which the production bill of material is defined.