Validate Received Production Bill of Material (timfc3250m000)
Use this session to validate the production bill of material (PBOM) received from PLM.
Note: This session can be accessed only if:
- The Engineering Revisions check box is selected in the Implemented Software Components (tccom0100s000) session.
- The Originating App field is set to PLM (Internal) or PLM (external) in the Item Base Data Parameters (tcibd9199m000) session.
This session can also be accessed using the Received Production Bills of Material (timfc3150m000) session.
option from the menu in theYou can only validate the received production bill of material with the Revision Status set to Received.
Field Information
- Selection
- Use the fields in the Selection group box to specify the range of received production bill of material that must be validated.