Check Production Bill of Material Consistency (timfc3200m400)

Use this session to to check for loops in the Production Bills of Material (timfc3100m000) session and conflicting settings in items in case of a (multi-level) bill of material structure.

Field Information

From Product

The product range to check for consistency.

Revision

The range of revisions to check for consistency.

Stop at first Loop

If this check box is selected, LN stops the check once a loop in the production bill of material (P-BOM) structure is detected.

Check Order System

If this check box is selected, the item order system is checked: if a component has the order system Planned, the product should have order system Planned.

Update

If this check box is selected, the order system is updated.

Check Unit Effective Supply

If this check box is selected, the unit effective material supply for the product is checked: if a component has unit effective supply, the product must have unit effective supply.

Update

If this check box is selected, the unit effective material supply for the product is updated.

Check Project Peg Indicators

If this check box is selected, the Mandatory Project Peg and Inherit Project Peg parameters in the Items (tcibd0501m000) session are checked for the product.

If the component has:

  • Inherit Project Peg

    The product should also have it checked.
  • Mandatory Project Peg

    The product must also have it checked.

Check Commingling Restrictions

If this check box is selected, the commingling restriction on materials or components linked tot the product are checked: if the commingling check box is selected for a component, it must be selected for the product.

Update

If this check box is selected, the commingling restrictions are updated.

Check License Tracking

If this check box is selected, the license tracking on materials or components linked to the product is checked: if the license tracking check box is selected for a component, it must be selected for the product.

Note: For this check box to be selected, the Restrict Commingling and Cost Peg Transfers per Item parameter in the Project Pegging Parameters (tcpeg0100m000) session must be selected.
Update

If this check box is selected, the license tracking is updated.

Check Trade Compliance

If this check box is selected, the trade compliance of the production bill of materials is checked: if trade compliance is selected for a component it must be selected for the product.