E-Item by MBC (tiedm3122m000)
Use this session to define and modify which engineering items are linked to an MBC line. If the E-items were generated using the Generate E-Items by MBC (tiedm3201m000) session, this session also enables you to apply changes.
Field Information
- MBC Number
-
The code of the MBC to which revisions are linked.
- Order Status
-
The order status.
- All Actions Must Apply to Item
-
If this check box is selected, the engineering items selected in the Include/Exclude E-Items (tiedm3121m000) session, to which all MBC lines are applicable, will be considered for change.
If this check box is cleared, the E-items selected in the Include/Exclude E-Items (tiedm3121m000) session, to which at least one MBC line is applicable, will be considered for change.
Note: The field relates to E-items which are both directly and indirectly listed in the Include/Exclude E-Items (tiedm3121m000) session. - Position
-
Select the position for the MBC item.
- Engineering Item
-
Enter the engineering item for the MBC.
- Description
-
The description or name of the code.
- Old Revision
-
The revision that is used as the basis to change an E-item ( Engineering Item field).
- New Revision
-
The new revision assigned to the E-item in the Engineering Item field.
See the E-Item by MBC (tiedm3122m000) for more details.
- Effective Date of New Revision
-
Enter the effective date for the new revision. This is the date on which the revision will take effect.