Production Order Work-in-Process by Cost Component (ticst0553m000)

Use this session to display the work in process (WIP) for production orders by cost component.

To start this session, start the Display Work-in-Process (ticst0550m000) session and set the Aggregation Level field to By Amount Type. Then, click Continue.

Field Information

Site

The site ID.

Note: Only visible if multisite functionality is active.

WIP Analysis Date

The date for which the work in process are displayed.

Production Order

production order

Calculation Office

calculation office

Project

project

Order Status

production order status

Shop Floor Planner

shop floor planner

Position

The position number in the Estimated Materials (ticst0101m000) session.

Operation

operation

Item

The item that is used as a material in production.

Reference Operation

The task performed in the operation.

Work Center

The work center where the operation was performed.

Machine Type

machine

Ownership

ownership

Possible values

Company Owned

company owned

Consigned

consigned

Customer Owned

customer owned

Return as Issued

When items are returned from the production environment to the warehouse, for example, because fewer items were required than issued for production, the original owner at the time of issue will become the owner again (unless the items are damaged).

Deferred

The date the ownership is transferred from supplier to customer is still unknown. The change date is determined after the items are picked, and depends on both the warehouse types involved in the goods transfer and the agreement between supplier and customer.

Not Applicable

Your own organization owns the inventory. Ownership behavior refers only to not-owned inventory.

Amount Type

The type of WIP transactions represented by this record.

Possible values

  • Completion

    A quantity of the main item is reported completed.
  • SLS Issue

    A completed item is delivered to a customer.
  • Materials

    Materials are issued for the production order.
  • Operation Costs

    Hours of work are reported for the production order.
  • Subcontr. Costs

    Subcontracting costs were made.
  • Surcharges

    Surcharges were charged to the production order.
  • Eff. Variance

    efficiency variances
  • Price Variance

    price variances
  • Calculation Var

    calculation office variance
  • WIP Transf. (In)

    A WIP transfer of an unfinished item into a work center for further processing.
  • WIP Transf. (Out)

    A WIP transfer of an unfinished item to the next work center for further processing.
  • Receipts

    Receipt of a completed item into inventory.
Cost Component

cost component

Currency

currency

Incoming WIP Value

The value of the WIP transactions related to unfinished items, materials, and spent hours put into the production order.

Booked Results

Result

Outgoing WIP Value

The value of the WIP transactions related to completed items transferred to inventory.

WIP Amount

The value of the work in process.

WIP Hours

The production hours of the work in process.